|
|
May 29, 2008 |
Ohio's Tenth Appellate District Addresses Priority Between Mechanics’ Liens and Mortgages; Prejudgment Interest on Mechanics’ Liens
|
On May 20, 2008 the Tenth Appellate District Court of Appeals issued an opinion
in Guernsey Bank v. Milano Sports Enterprises, LLC holding on several
issues of priority between mortgages and mechanics’ liens as well as the
application of prejudgment interest on mechanics’ liens.
In the case, Joseph Milano purchased property containing an indoor tennis court
which he sought to convert into an ice rink. Before purchasing the property,
Milano entered into a lease agreement allowing the renovations to begin, and
contracted with several companies to perform work or provide materials. The
purchase of the property was financed through a mortgage note with Guernsey
Bank, and all documents were recorded on July 10, 2003. Milano and his company,
Milano Sports Enterprises, LLC were parties to this note. When the work and
materials went unpaid, the contractors filed mechanics’ liens with the
Recorder.
On January 27, 2004 Guernsey filed a foreclosure action against the Milanos and
their company, including as defendants all of the contractors that had recorded
mechanics’ liens. Guenrsey prevailed at summary judgment and the property was
foreclosed and sold by the Sheriff. Guernsey purchased it at the appraised
value of $525,000. The lien-holding defendants moved for summary judgment
against Guernsey, asserting the priority of their liens. Guernsey in turn filed
summary judgment motions against each defendant. The trial court found for the
lien-holders, granting them summary judgment and ruling their liens had
priority over Guernsey’s mortgage. Prejudgment interest was included in the
amounts awarded. Guernsey’s motion for summary judgment was denied.
On appeal, Guernsey challenged the validity and priority of the liens, and the
awarding of prejudgment interest. Guernsey challenged the validity of one lien
as it did not correctly state the amount due. However, as the party moving for
summary judgment, Guernsey bore the burden of producing evidence that the
amount was incorrect. In the absence of evidence, and based solely on
Guernsey’s conclusory statements, the Court affirmed the validity of the lien.
Guernsey attacked the validity of a lien based on the work described in the
lien being outside the ambit of the lien-holder’s contract. However, the Court
affirmed the validity of the lien, as the contract granted the company a broad
mandate regarding electrical work.
As to priority, the Court held that mechanics liens under R.C. 1311.13(A)(1)
may take effect before being recorded, while mortgages take effect upon their
recording. Without a notice of commencement filed, the mechanics’ liens took
effect from the “date the first visible work or labor [was] performed or the
first materials [were] furnished.” The first work or delivery of materials
occurred on June 16, 2003, almost a month before the recording of the mortgage.
As such, all of the mechanics’ liens properly filed took effect on that date.
The Court noted that R.C. 1311.13 requires courts to focus on the first visible
work or delivery of materials as opposed to the results of actions taken on
site.
Guernsey also alleged that its mortgage fell under R.C. 1311.14, the
construction mortgage statute. This statute creates an exception to the general
rule that a mortgage is subordinate to mechanics’ liens with an effective date
prior to the mortgage’s recording. Under the statute, a mortgage used to
finance improvements or pay off prior encumbrances has priority over mechanics’
liens. Guernsey’s mortgage had been used to pay off a prior mortgage on the
property. In support of this fact, Guernsey provided a settlement statement.
The trial court ruled this evidence inadmissible, and as such, the Court could
not consider it. The priority of the liens was affirmed.
Finally, Guernsey challenged the application of prejudgment interest to the
award. Following established precedent, the Court stated the nature of a
mechanics’ lien is that it arises from law and not from a written instrument or
verbal contract, precluding the availability of prejudgment interest.
The Guernsey holding may not break new legal ground, but highlights the
importance of basic procedures regarding mortgages. Early recording of the
mortgage, alongside keen attention to detail regarding work being performed or
materials delivered to the property can become deciding issues regarding
priority between a mortgage and a mechanic’s lien. Recordkeeping and
evidentiary issues are highlighted, as Guernsey may have prevailed had it
submitted proof of the actual amount due on one of the liens. Further, if
Guernsey had proven that its mortgage was a construction mortgage it may have
defeated the mechanics’ lien priority. These important considerations can make
the difference between the collection of an unburdened mortgage or one affected
by mechanics’ liens.
This E-alert was prepared by
Francisco Luttecke. Please contact any member of the
Bricker & Eckler Creditor Rights & Bankruptcy group for more
information.
|