Home |  Contact |  Site Map

 
 

Resources

Service Description
Attorney Directory
Services & Experience
Publications
 


Related Services

OSHA
Green Strategies
Government Relations
Public Sector
Education
Health Care
 

   Construction

 Print-Friendly Version
More Public Ownership articles

Commissioning - Is it the Answer to HVAC Problems?

By: Maureen P. Taylor

Reprinted from July 2003 ohioconstructionlaw.com

The Problem. Which system in a new building is likely to require 15 to 25% of the construction budget and cause most of the headaches after construction is finished? If you answered the HVAC (heating, ventilation and air conditioning) system, either you have been reading back issues of ohioconstructionlaw.com (specifically, the March 2003 issue), or you really know the construction industry.

The “rule of thumb” for the cost of an HVAC system met with general agreement at the Roundtables sponsored last winter by Bricker & Eckler LLP’s Construction Law Department. The problems encountered with HVAC systems surfaced repeatedly in Bricker & Eckler’s annual surveys of school construction projects over the last four years. Year after year, more schools reported problems with the HVAC system than with any other system, including roofing. In 2002, for instance, 40% of respondents reported that their HVAC systems either had problems requiring considerable efforts to correct or had problems that were still not corrected at the time of the survey.

With all of the improvements in technology, why don’t HVAC systems always work as their owners expect them to work? The technological sophistication of the systems themselves may be partly to blame. Today’s systems require more above-ceiling installation, have to meet more demanding codes, and have much more complicated controls than the older systems. There are more design options than ever before, and therefore more opportunities for design problems.

At the same time, as Tony Furst, Senior Project Administrator for Commissioning Services with Heapy Engineering, Inc., points out, the construction industry has gotten more and more competitive. Increased competition encourages contractors to cut costs by installing their equipment and then walking away, without providing some of the services that used to be standard. The result? HVAC and other systems that operate at less than peak efficiency - sometimes a lot less.

Is there an answer, a way to assure that these expensive systems will operate as intended and designed, saving the owner in the long run on operating costs? Many in the industry think that the process of Commissioning provides at least a partial answer. In the last decade or so, Commissioning for new buildings has gotten increased attention.

What Is Commissioning? The standard definition comes from an influential publication from ASHRAE, the American Society of Heating, Refrigeration and Air-Conditioning Engineers, Inc.:

[Commissioning is] the process of ensuring that systems are designed, installed, functionally tested, and capable of being operated and maintained to perform in conformity with the design intent. [The process] . . . begins with planning and includes design, construction, startup, acceptance and training, and can be applied throughout the life of the building. [ASHRAE Guideline 1-1996, “The HVAC Commissioning Process,” Clause 4.2]

As the Guideline says, “Owners can use the process to achieve quality from the start in lieu of inspecting for quality or modifying the system after the facility is occupied.”

What “systems” are involved in the Commissioning process? HVAC, of course, which includes air handling systems, hot water, chiller, and controls, but commissioning specifications can also include such systems as the electrical switchgear and the fire detection system.

Although the Ohio Basic Building Code does not require Commissioning (yet), the Ohio School Facilities Commission recognizes its importance. Furst says that Heapy Engineering has contracted to develop Commissioning specifications to be included either in an addendum to or in a revision of the OSFC Design Manual. When the new specifications are issued, he expects Commissioning to be required for any project still in the design phase. So many school districts - and many contractors - will need to understand what Commissioning entails. And if the schools require it, can other public construction be far behind?

To visualize how Commissioning works, consider the same hypothetical project with and without Commissioning.

How Does It Work Without Commissioning? In the typical construction project - without Commissioning - the contractors are responsible for seeing that their own systems comply with the design documents and are working. Most follow the specifications, but occasionally, in Furst’s experience, a contractor will “throw the spec away” and do something else. Either the Mechanical Engineer or a Construction Manager with expertise in HVAC systems may catch some nonconforming work. But a CM can’t be an expert in everything, so some problems get missed. To a certain extent, a CM has to rely on the contractors to do their jobs.

Once the equipment is installed, a TAB contractor (in charge of Testing, Adjusting, and Balancing) tests out the equipment and prepares a TAB or “balance” report listing any deficiencies noticed. TAB contractors can be prime contractors but are more commonly subs to the mechanical contractor. If so, they submit their balance report to the mechanical engineer in draft form. The final balance report from the mechanical contractor may or may not be the full report of the TAB contractor. And TAB contractors can miss things, too - sometimes whole systems, such as the chilled water system in one recent project Tony Furst recalls.

As the building nears Substantial Completion, the process of field inspection generates punchlists of deficiencies or exceptions in the various systems. Does each system comply with acceptable industry standards and with the shop drawings? If not, a note of the deficiency is made on the punchlist. But no one checks to see if the system is working at peak efficiency; the questions are merely (1) is it the equipment called for, and (2) is it operating?

If everyone has complied with the contract, installed the equipment as designed, and done a good job, all systems may be go at the start. The building is occupied, and the contractors leave.

Then the seasons change, different equipment kicks on, and the maintenance staff has some questions. Why isn’t Room 106 as cool/warm as Room 206? Why do the fans make so much noise first thing in the morning? Why are the electric bills so much higher than they were in the old building? Dissatisfaction builds, and eventually someone calls a meeting of the contractors involved. After much finger-pointing, everyone agrees that something should be done. But who should do it, and who should pay for it? If the situation is bad enough, this can lead to an all-out dispute that may only end before an arbitrator or in a court of law.

How Does It Work With Commissioning? With Commissioning, the same project would involve an additional professional, the “Commissioning Authority” or “Commissioning Agent.” (Take your pick; you can abbreviate either one “CA.”) The CA can be an employee of the owner, the Construction Manager, or an independent professional. The role of the CA, according to the ASHRAE Guideline, is to represent the owner’s needs and implement the overall Commissioning process, from the program phase of the project through at least the first year of operation.

So the CA starts as soon as the project is underway. The CA reviews the plans and specs to be sure all items related to the HVAC system are complete and adequate to do the job as the owner intends. Initially, the CA works with the design professionals to prepare a Commissioning Plan that will evolve through each phase of the project. In the program phase, part of the Commissioning Plan includes identifying the members of the Commissioning Team, which will be led by the CA and may include nine or more other individuals:

  1. The Mechanical Engineer;

  2. The General Contractor’s Representative(s);

  3. The Controls Contractor’s Representative(s);

  4. The Sheet Metal Contractor’s Representative(s);

  5. The Electrical Contractor’s Representative(s);

  6. The Fire Detection Contractor’s Representative(s);

  7. The Mechanical Contractor’s Representative(s);

  8. The Air Balance (or TAB) Contractor’s Representative(s); and

  9. The Owner’s Representative(s).

Shortly after the contracts are awarded, the CA calls together all the Team members for a Commissioning Kickoff Meeting. From this meeting should emerge tentative schedules for inspections, systems testing, balancing, performance testing, and training the owner’s personnel. Thus begins the process of coordinating the contractors, subs, suppliers, and owner’s representatives.

Once the equipment is installed, the CA will coordinate the inspections, check the work of the TAB contractor, receive and review maintenance manuals, witness the startup of each system, and document, document, document. According to Furst, documentation is a strong point of the Commissioning process. For a typical school, for instance, the assembled Commissioning documents will fill a three-inch binder.

An important item in the documentation is the Functional Testing Log, a specific checklist for each system (the chilled water system and the air handling unit, for instance) that specifies in minute detail the tests to be performed and the responses desired from the equipment. If the responses are below par, the appropriate contractor must adjust or replace the less-than-satisfactory equipment. (This requirement must be written into each contract, so that each contractor recognizes the obligation to correct any deficiency noted on the Log.)

When the checklist is completed, everyone involved signs off on the Log. The appropriate contractors and the Construction Manager certify that the system and equipment involved meet the functional requirements described in the Log. The CA and owner’s representative sign to show they have witnessed the testing and approve the results. Both the owner and the contractors have assurance that the system is working at peak efficiency.

All of this documentation is invaluable when it comes to training the owner’s operation and maintenance staff. Heapy Engineering makes a point of inviting the maintenance staff to all of the functional testing sessions. When it is time for the final training session, each contractor submits an outline of what it plans to cover, and the contractors and CA work together to educate those who will be running the equipment on ways to get the most efficient performance from it.

Then the building opens, and the contractors move on to other projects. But the Commissioning Agent or Authority continues under contract for the next year (or longer, if the project is particularly huge or complex). When the seasons change and new equipment shifts into gear, the CA is there to witness the startup and to monitor the systems’ performance. Everything should continue to operate smoothly. But if it doesn’t, the CA has the original documentation to consult. A quick check of the Functional Testing Log should reveal what has changed since the beginning, when the system was working properly.

Where Do You Find a Commissioning Agent? Opinions differ on whether the Commissioning Agent or Authority should be independent from the other players in the construction process. The ASHRAE Guideline calls it “logical” to choose an employee of the owner to fill the role. Others argue for independence.

Many owners, of course, would have trouble finding a person on-staff to meet the suggested qualifications. These, according to ASHRAE, should include at least these six “minimums”:

  • At least five years of construction experience;

  • Experience or training with the ASHRAE commissioning process;

  • Controls and instrumentation experience;

  • Knowledge of specific types of buildings and HVAC systems, and experience with them;

  • Excellent oral and written communication skills; and

  • Experience working with multidisciplinary teams.

Other qualifications ASHRAE recommends include design experience, operation and maintenance experience, knowledge of testing, adjusting, and balancing, knowledge of life safety codes, and professional registration.

If no employee of the owner quite fills the bill, a check of engineering firms and construction management firms may be in order. Since Commissioning is still relatively new, many consulting engineers are just getting into the Commissioning business. According to Tony Furst, there is no nationally accepted certifying authority for Commissioning Agents, although the National Environmental Balancing Board is working to develop one.

What’s It All Going To Cost? Part of drawing up the initial Commissioning Plan includes developing a budget for the process, an estimate of what it is all going to cost. Much depends, of course, on the size and complexity of the facility. Furst thinks a good rule of thumb is that the Commissioning fee should run about one to two percent of the Architect’s fee.

Will the contractors increase their bids, knowing that the project involves commissioning? The answer to that varies, depending on the contractor. In Furst’s experience, the more responsible contractors will see commissioning as a coordinated effort to assure that what ought to be done anyway is being done by everyone. Since no additional work is called for, they see no reason to increase their bids. Others may add as much as three or four percent to their bids.

Is This Expense Really Necessary? For some owners, Commissioning is a hard sell. They agree with one Roundtable participant who put it this way: “Look, I’m already paying an Architect, a Mechanical Engineer, a Mechanical Contractor, a Construction Manager, a Controls Subcontractor, and an Air- Water Balance Subcontractor. Do I really have to pay for a Commissioning Agent, too? Why can’t they all just do their jobs right, so my HVAC system will work properly?”

There are really three answers to this question, with some truth to each.

The first and simplest answer is that the skeptical owner is right. If all the jobs were done properly, then the system should work properly. In the best of all possible worlds, Commissioning would be unnecessary.

But we don’t live in the best of all possible worlds, at least not yet. The second and more realistic answer lies in the description of the problem itself: The sophisticated technology of today’s systems makes coordination of the various contractors and their equipment vital. It is not enough that each piece work properly in isolation. Each piece must be adjusted, calibrated, and integrated with the other equipment in the building. The whole is really equal to more than the sum of the parts, and only the Commissioning Agent knows and understands the whole.

The third answer is that it is possible to draft the frontend documents to achieve many of the benefits of Commissioning without calling for a separate Commissioning Agent. One way to do this is to involve the Mechanical Engineer at an earlier stage than usual.

For instance, in many of the Owner-Architect Agreements drafted by Bricker & Eckler attorneys, the Schematic Design Phase calls for an early meeting in which the Architect, Mechanical Engineer, Construction Manager and owner review the owner’s expectations of the HVAC system and discuss the options available, the costs of operation and maintenance, and the costs and benefits of the Commissioning process, a life cycle cost analysis, and a maintenance agreement for the HVAC system. Such a meeting should lead to shorter follow-up meetings in later phases of the construction process.

System testing during the first year of operation can also be included in the front-end documents, of course. It is an open question whether these contractual additions will actually achieve the results of Commissioning without the costs. If much of the Commissioning Agent’s work is built into the Architect’s or Mechanical Engineer’s role, won’t their fees be increased accordingly? That’s certainly a possibility.

Do the Benefits Justify the Costs? The costs of Commissioning should be balanced against what Furst and others in the industry see as the considerable benefits of the Commissioning process:

  • Receiving a building with few or no system deficiencies;

  • Optimal performance that results in much lower energy costs (Furst tells of one school where the annual cost of energy works out to $2.50 per square foot);

  • Assured compliance with warranty requirements;

  • Minimal complaints from occupants; and

  • The joy of avoiding the headaches that come with moving into a non-functioning building or one that just doesn’t work the way it should.

How Do You Get Started? If you want to learn more about the Commissioning process - or if you’ve already decided you want to include it in your next project - a good place to begin is with the ASHRAE Guideline 1-1996, “The HVAC Commissioning Process.” The Guideline can be ordered on the Internet, either in a print or a downloadable version.

Other resources available from the ASHRAE online bookstore will help you calculate the costs of Commissioning, establish Commissioning fees, and develop specifications and RFPs for Commissioning services. These should prove invaluable as you begin at the beginning, revising your contracts and other front-end documents so that they include Commissioning.


Thanks to Tony Furst of Heapy Engineering, Inc., for reviewing and contributing to this article.

 

Special Features

Visit our special topical resources
Construction Resource Centers

What's happening in the 127th Ohio General Assembly?
Construction Legislation

Join the Bricker & Eckler Construction
Fellowship program

Doing business with the State of Ohio or its various cities, counties, and localities? Visit our resources for assistance
Government Contracting and Procurement

Upcoming
Construction Seminars
 


Newsletter

Read our latest issue of Brickerconstructionlaw.com
November 2008 Newsletter

Read past editions of Brickerconstructionlaw.com & ohioconstructionlaw.com

Subscribe to Brickerconstructionlaw.com
 

 

Copyright 2005-2008, Bricker & Eckler LLP, all rights reserved.  Please read our Privacy Notice.
The words Bricker & Eckler and its logo are registered trademarks of Bricker & Eckler LLP