Hindsight About Unforeseen Site Conditions
A Rare Successful Type II Differing Site Conditions Claim
By: Doug Shevelow, P.E.
Reprinted from May 2007 Brickerconstructionlaw.com
Back in January of 2006, this column discussed proving a Type II differing site
conditions claim, one for costs attributable to site conditions that differ from
the known and usual. I noted that Type II claims are fact-intensive and
difficult to prove, making successful Type II claims rare. For an example of a
successful claim (albeit only partially successful), I summarized a case from
the U.S. Claims Court where an earthen dam contractor was able to recover for
some of its costs when the soils it was handling behaved unexpectedly after
becoming wet.
It has happened again. This month the Armed Services Board of Contract Appeals
gives us that rarest of gems, a case where a contractor vindicated its
entitlement to whatever it could prove as damages on a Type II differing site
conditions claim. The case, Appeal of Parker Excavating, Inc., 2006
ASBCA LEXIS 18, arose out of the construction of several miles of underground
electrical conduits at Fort Carson, Colorado.
There were no soil borings or other type of underground investigation to
determine exactly what the contractor could expect in the subsurface, which is
most likely why this was not a Type I differing site conditions case—there was
nothing in the contract documents to compare actual conditions to. But it was
known that hard rock existed in the area, generally making subsurface work
difficult.
Instead of open trench methods, the contractor was using directional boring to
advance a six-inch diameter conduit. For several months, the contractor was
hampered by slower-than-expected production and frequent boring machine
breakdowns. It fell behind schedule. The contractor attributed its problems to
construction debris in the subsurface, which consisted of concrete foundation
pieces, rebar, asphalt and other waste material. The contractor informed the
contracting officer of these conditions and documented them in its crews’
timesheets, foreman’s diary and daily superintendent reports. Sometimes samples
of the debris were retrieved as the drillhead was retrieved back through the
borehole. Other times the debris was discovered when the drillhead became stuck
and had to be rescued through an open excavation.
The contracting officer denied the contractor’s $74,000 claim, stating that the
claim was not timely made, that the contractor’s problems were attributable to
operator error, and that the contractor should have anticipated difficult
boring conditions because the presence of hard bedrock was well known in the
area.
The Armed Services Board of Contract Appeals thought more than hard bedrock was
involved. It overruled the contracting officer, declaring that the contractor
was entitled to a Type II differing site conditions claim under Federal
Acquisitions Regulation 52.236-2. The Board remanded the case back to the
parties to negotiate a value on the claim.
The Board noted that the contractor, too, was concerned that its problems could
be attributable to operator error. It brought in a new operator, who
experienced the same problems—slow production and frequent equipment
breakdowns. The Board also found numerous instances where the contractor voiced
its concerns with the problems it was having with the construction debris. The
Board even noted the government’s own documents acknowledging the contractor’s
complaints and requests for guidance early on in the project. Finally, the
Board held that even though hard bedrock and construction debris can both make
horizontal boring more difficult, they are distinctly different phenomena. It
would be fundamentally unfair to assume that they would cause identical
problems for the contractor.
This case holds several obvious, yet important lessons. Owners who forego a
subsurface investigation before bidding subsurface work are asking for trouble.
On the contractor’s side, underground projects on older, redeveloped sites run
a higher risk of subsurface interferences from abandoned foundations and
demolition debris. When facing a bid on a project like that, a contractor needs
to be sure that the contract protects it from differing site conditions.