Hindsight About Unforeseen Site Conditions
Defining a Reasonable Site Investigation
By: Doug Shevelow, P.E.
Reprinted from September 2005 ohioconstructionlaw.com
How can a contract provision requiring a bidder to
make a reasonable site investigation help to defeat a
Contractor’s differing site conditions claim? That was
the topic of the October 2003 column, and it came up
again recently in a case from the Federal Court of
Claims. But first, some background . . . .
Generally, a Contractor is expected to make a reasonable
investigation of the project site to determine if
subsurface or unforeseen conditions may pose a problem.
This general duty is almost always bolstered by
a contract clause requiring the Contractor to make a
“thorough site investigation” or “pre-bid site inspection.”
The construction contract often includes
an admission by the Contractor that it has made a
thorough site investigation and is familiar with all site
conditions.
Contractors who fail in their duty to inspect the site
are generally denied additional compensation to manage
conditions that could have “reasonably” been
inferred from a thorough site investigation. But
determining what is “reasonable” can be difficult.
Prior Case Law
Most courts do not find an implied duty for the Contractor
to conduct an invasive investigation. For
example, see, I.A. Construction Corp. v. PennDOT,
(Pa. Commw. 1991), 591 A.2d 1146. But for a case
where the Contractor should have at least “scratched
the surface” because of the boring logs’ indication of
the potential for a peat bog, see Appeal of Parkland
Design & Development Corp., IBCA No. 1442-3-81
(1982).
However, the contract may require bidders to make
their own subsurface investigation. The courts are
generally split on whether this is an enforceable provision,
some ruling it is not because of the
impracticality and cost of multiple bidders’ performing
disruptive activities, especially when the Owner
has made no provisions to facilitate the investigations.
Department of Transportation v. P. Dimarco
& Co., Inc. (Pa. Commw. 1998) 711 A.2d 1088, is a
case in point.
Sometimes, though, Contractors are relieved from
making a thorough site investigation when the Owner
does not make sufficient provisions and allowances
for the Contractor to do so. Two cases holding this
are Clark Brothers Contractors v. State of Montana
(Mont. 1985), 710 P.2d 41, and Appeal of Dayton Construction
Co., HUD BCA No. 82-746-C34 (1983) (bid
periods were too short to allow bidders to confirm
elevations).
Regarding facility conditions, Contractors have been
held responsible for observing that an existing catwalk
would conflict with proposed ductwork (Appeal
of American Construction & Energy, Inc., ASBCA
No. 52032 (2000)), and that certain pipes and valves
did not really exist (Appeal of Swepco Corp., ASBCA
No. 25118 (1981)).
On the other hand, Contractors have been deemed
not responsible for discovering conditions that would
have required destruction of the Owner’s property.
For example, see Appeal of Southern California
Roofing Co., PSBCA No. 1737 (1988) (extra layer of
roofing not discoverable without cutting through top
layer of roof).
Contractors are also generally excused from having
to use extreme measures to investigate. A Contractor
was not required to use a high pressure
hose to determine the true extent of rotten
wood in Appeal of Midwest Industrial
Painting of Florida, Inc., ASBCA No. 35194
(1990).
The Latest Case: Conner Brothers
These cases help to establish rules and
reference points for determining the “reasonableness”
of a prebid site investigation.
A U.S. Court of Federal Claims case from
this summer elaborates on this “reasonableness”
concept and gives us a new rule.
In Conner Brothers Const. Co. v. U.S. (June 10, 2005),
65 Fed. Cl. 657, a mechanical subcontractor and General
Contractor lost a differing site conditions claim
for nearly $250,000. The claim was based on extra
costs in reconnecting ductwork as part of an approximately
$7 million renovation of a V.A. hospital.
The contract documents required that the existing
ceilings be demolished and replaced (while the
hospital remained in service). The ceiling demolition
required that new HVAC diffusers be installed and
connected to the existing HVAC duct system. Here
is where the problem occurred. Both Contractors
assumed that the existing diffusers were connected
to the ductwork by flexible connectors, meaning that
the new diffusers could be connected the same way.
Unfortunately, the old diffusers were connected
directly to the duct system. There was not enough
clearance to accommodate flexible connectors. This
problem was exacerbated by the fact that the
locations of the new diffusers were different from the
old locations.
The contract included a standard site investigations
clause (Federal Acquisition Rule 52.236-27) requiring
the Contractor to acknowledge “that it has taken steps
reasonably necessary to ascertain the nature and
location of the work . . . [and] satisfied itself as to the
. . . obstacles to be encountered insofar as this information
is reasonably ascertainable from an inspection
of the site . . . .”
It also included a standard differing site conditions
clause (Federal Acquisition Rule 52.236-3) providing relief for either a Type I condition (different from what
is represented in the contract documents) or Type 2
condition (conditions of an unusual nature).
The Contractors did investigate conditions above the
ceilings - where they could. Access above plaster
ceilings was especially difficult, available only
through a few access panels. Here the Contractors
were unable “to see past a jumble of wires or pipes
and ducts.”
This is where the Contractors lost the sympathy of
the court. It held with regard to the obscured view:
“that fact alone should have alerted a reasonable,
experienced contractor both of the need to inquire
with the government as well as the likelihood that
there might well be a space problem with the void
area above the ceiling.” So the sin here was not
the failure to inspect above the ceiling, but a
failure to inquire further when the inspection
was hindered.
And thus a new rule is added to the law of differing
site conditions: Bidders must inquire further whenever
their site investigations are hampered by site
conditions. (Smart bidders will carefully document
this inquiry as well as any response.)