|
The Case Everyone is Talking About -
Cementech
May/June 2005
By: Maureen P. Taylor and
Vladimir P. Belo
VIEW OR PRINT ARTICLE IN PDF FORMAT
Read about the Ohio
Supreme Court decision in Cementech issued June 28, 2006
What risks does a public owner
run if it rejects a bidder it should have accepted?
Earlier this month, a decision from
the Summit County Court of Appeals
changed the answer to that question, and
everyone interested in the legal aspects of
construction has been talking about the
Cementech decision ever since. This article
will tell you why the case may be important,
how the dispute got to the Court of Appeals,
what the law was before the Cementech decision,
and how that may have changed - at
least for the time being. The article concludes
with a look ahead and some advice
on how both public owners and disappointed
bidders can protect themselves from
costly mistakes.
What the Buzz Is All About
On rare occasions, a court sets out to change the
law. On even rarer occasions, it announces its intention
to do just that. Both happened earlier this month
when, on April 13, the Summit County Court of Appeals
issued its second opinion in Cementech, Inc. v.
City of Fairlawn.1
The latest decision seems to be the focus of
conversation for nearly everyone involved in some
aspect of public construction in Ohio.
Why all the attention on a bidding dispute arising
from construction of a service road for the City of
Fairlawn? For the first time in Ohio, a court said that
a disappointed low bidder might be entitled to more
than injunctive relief and even more than the cost of
preparing its bid. Admitting that “we are setting a
precedent,” the Court of Appeals said that if the
wrongfully rejected bidder could prove its lost profits,
it might recoup them from the City. It sent the
case back to the Court of Common Pleas in Summit
County so that the bidder, Cementech, Inc., could
prove the amount of the profits it lost when another
bidder was awarded the contract.
Unless the Ohio Supreme Court decides that the Court
of Appeals is wrong, this will become the law of Ohio,
or at least the law of the Ninth District (which includes
Summit, Medina, Lorain, and Wayne
Counties). If the Ohio Supreme Court should decline
to decide the issue, earlier decisions in Trumbull
County, Cuyahoga County, and Licking County
would prevail and make injunctive relief - rather than
damages - the only remedy available to disappointed
bidders in those jurisdictions. A Supreme Court decision
affirming this month’s decision of the Court of
Appeals would of course make the Cementech decision
the law of the whole State.
How the Case Got to This Point
The dispute arose back in 2001 when the City of
Fairlawn opened bids for the construction of a service
road, including Addendum No. 1, which added
“obtaining and installing 54 Cleveland Select Pear
Trees.” Cementech was the apparent low bidder with
a bid of almost $600,000. But the City was required by
statute2
to select the
“lowest and best” bidder, and the City Law Director,
reviewing the bids on opening day, determined that
the Cementech bid apparently omitted the 54 pear
trees. The Law Director wrote to Cementech on the
same day with the news that its bid had been rejected
because the failure to include the addendum made it
non-responsive to the bid specifications.
Cementech protested and received a hearing before
the Board of Audit and Review, which agreed with
the Law Director. The City Council awarded the service
road project to the next lowest bidder, and
Cementech filed suit in the Summit County Court of
Common Pleas on the last day of 2001.
Cementech’s complaint sought compensatory damages
in excess of $75,000 for the City’s alleged breach
of competitive bidding law. Alternatively, the complaint
sought injunctive relief (including a temporary
restraining order, preliminary injunction, and permanent
injunction) that would have required the City
either to award the project to Cementech or to order
the project to be “relet and rebid,” thereby allowing
Cementech another opportunity to be awarded the
contract for the project.
One week after Cementech filed the complaint, the
trial court denied in toto the requested injunctive relief.
In a terse two-page order, the court determined
that Cementech had failed to establish an entitlement
to injunctive relief under the well-established standards
for granting such relief in Ohio. Specifically,
the court decreed that Cementech had failed to show
either (1) a likelihood of success on the merits of its
complaint or (2) irreparable harm.
The issue of damages remained for trial, unless the
City could get a summary judgment deciding it on
purely legal grounds (without the need for a trial). So
the City moved for summary judgment, arguing that
the City had not abused its discretion in rejecting
Cementech’s bid. Because the Law Director could
reasonably determine that Cementech’s bid contained
a material irregularity (i.e., the omission of the 54 pear
trees required by the project specifications), the City
argued that there was no basis for liability under the
applicable competitive bidding laws. For its part,
Cementech opposed the City’s motion by arguing
that (1) the City’s Law Director acted without valid
authority in rejecting the bid, (2) the pear trees were
not required to be included with the bid, and (3) in
any event, the omission of the pear trees was not a
“material” deviation from the project specifications.
The trial court agreed with the City and granted judgment
in its favor. The omission of 54 pear trees was
material, according to the court, and Fairlawn’s ordinances
granted the Law Director the authority to
review bids to determine their responsiveness: Did
they materially comply with the City’s bid specifications?
In this case, the trial court thought that
Cementech’s bid did not, so rejecting it was not an
abuse of discretion.
So the case took its first trip to the Court of Appeals
for Summit County, a trip that started with
Cementech’s appeal and ended with the first
appellate decision on June 18, 2003.
The first decision focused on the issue of authority.
Did the City Law Director exceed his authority when
he notified Cementech that its bid had been rejected
on the same day the bids were opened, before any
bids were even submitted to the City Council? Unanimously,
the three-judge panel agreed that this was a
mistake. The relevant City ordinance, Section 234.01
of the Codified Ordinances of the City of Fairlawn,
established, at best, that the Law Director “had the
authority to give a legal opinion as to whether
Cementech’s bid met the city’s specifications.” He
could advise the City Council, but, according to the
court, he could not make the ultimate decision to
remove Cementech’s bid from consideration. The
Court of Appeals therefore returned the case to the
court for further litigation.
Once more the City sought summary judgment, but
this time it was turned down. The case went to trial
on just one issue: damages. Before trial, the judge
requested briefs from both sides on what would be
the appropriate measure of damages. As expected,
the two views strenuously differed:
The City contended that Ohio law did not entitle
Cementech to recover monetary damages for lost
profits. The only remedies available to Cementech
were injunctive relief (which had already been denied)
and a declaration stating that the City had wrongly rejected the contractor’s bid. A lost profits
award on top of these remedies would be bad
public policy, as it would effectively make the City
“pay twice on the same project.” If there were to
be any money damages, the City argued that Ohio
law might permit the contractor to recover its bid
preparation costs - but only in “extraordinary circumstances,”
which the City said were not present
in this case.
Cementech argued that a disappointed bidder
should be granted “more than a hollow victory in
the form of nominal bid preparation costs.” Allowing
the City to wrongly deny a bid without
liability for lost profits would do little to prevent
cities from ignoring the competitive bidding laws,
Cementech argued. Additionally, it argued its entitlement
to recover its attorneys’ fees incurred as
a result of the City’s wrongful conduct.
Once again, the trial court agreed with the City, capping
the potential damages at the bid preparation costs
even before trial. Because the City had already
paid for the project once, the court
determined that public policy dictated that
the city’s taxpayers not have to pay for it
again. However, relying upon a precedent
set in Mechanical Contractors Assn. of Cincinnati,
Inc. v. University of Cincinnati3, the court decided that
Cementech could recoup its bid preparation
costs in the event the jury ruled in
Cementech’s favor. Cementech could not,
in any event, recover its attorney’s fees because
there was no Ohio statute that allowed
recovery of attorney’s fees for a prevailing
plaintiff in a case like this one, the court said.
Cementech effectively abandoned its quest
for attorney’s fees at this point.
The case proceeded to trial, with the jury
finding in favor of Cementech but awarding
it less than the full amount of its bid preparation
costs. The $3,725.54 jury award - about half of
the requested bid preparation costs - was symbolic.
As some jurors explained to Robert Hunt, attorney for
the City, in a post-trial briefing, the $25 was for “General
Note 25 in the specifications” (the much-debated
pear tree clause) and the 54 cents was a penny for
each pear tree.
Even though Cementech won, it was not happy with
the award. So it appealed for the second time to the
Court of Appeals for Summit County. This time it
made a plea for the recovery of lost profits and also
resurrected the appeal for attorney’s fees. The court
heard oral arguments just last month and issued a
speedy decision on April 13.
The State of the Law Before Cementech
Generally, courts decide issues based in large part on
how earlier courts have decided similar issues. On the
issue of damages available to a wrongly rejected bidder,
four Ohio courts had issued opinions, and the
Cementech court touched on all of them before deciding
to go its own way on a public policy argument.
Three of the earlier courts - Trumbull
County, Cuyahoga County, and Licking
County - had refused to grant money damages
to a disappointed bidder. All had
followed basically the same reasoning,
which first appeared in Hardrives Paving
& Construction, Inc. v. City of Niles4.
Hardrives. In Hardrives the City had accepted
a bid that was just $3.90 higher than
Hardrives’ bid for road construction, letting
the decision turn on criteria not
included in the bid documents (availability
to pave additional streets never mentioned
in the bid documents, basically some unwritten
alternates). Hardrives failed to get
a requested injunction to stop the construction.
Nor could it get damages in the form
of lost profits because the Trumbull County
Court of Common Pleas ruled that the City
had not abused its discretion when it rejected
Hardrives’ bid.
On appeal, the Eleventh District Court of Appeals
(which covers Trumbull, Portage, Geauga, Ashtabula
and Lake Counties) found that the trial court had been
right about some things and wrong about others. For
instance, it was right to turn down Hardrives’ request
for a mandamus order, as the trial court could not order
the City to award a contract to a certain bidder. But the
court had been wrong not to grant a declaratory judgment,
effectively declaring that Hardrives had a right
to the award of the contract because the City had
abused its discretion in using “unannounced criteria”
to select a bidder. The court had been right, though,
on the remaining issue of money damages. The appellate
court ruled that they were not available to
disappointed bidders, citing two reasons:
Injunctive relief and money damages were generally
mutually exclusive. Injunctive relief was
only available in situations where money damages
were not. “Thus, the fact that injunctive
relief is available generally indicates that a monetary
award is not available for lost profits.”
Money damages would go against the public
policy underlying the competitive bidding statutes,
which is “to protect both the public and
the bidders themselves.” Granting an award of
money damages to Hardrives would protect the
bidders at the expense of the public, “because
the public would have to pay the contract price
of the successful bidder plus the lost profits of
an aggrieved bidder. However, if injunction is
the sole remedy, both the public and the bidders
themselves are protected.”
The Ohio Supreme Court declined to consider the
case, and the reasoning in Hardrives went on to influence
other courts.
Cavanaugh and Midwest Service Management. In
the next seven years, the Hardrives decision influenced
two other courts to reject the availability of
lost profits for disappointed bidders: Cavanaugh
Building Corp. v. Board of Cuyahoga County Commissioners
(Cuyahoga App. 2000)5 and Midwest Service Management, Inc.
v. Licking Valley Local Board of Education6.
Cavanaugh arose from a county building project
where the low bidder, Cavanaugh, had provided faxed
signatures rather than originals on some required
forms. Cavanaugh sought an injunction, noting in its
Complaint that “an award of lost profits is not an
appropriate remedy to an aggrieved contractor under
Ohio law.” But at trial, it introduced evidence of lost
profits and argued that the County had consented by
implication when it failed to object. Still, the trial court
refused to award lost profits, and Cavanaugh appealed.
Citing to Hardrives, the Court of Appeals held that
“money damages for lost profits is not an available
remedy for an unsuccessful bidder against a contracting
authority. An unsuccessful bidder is limited to
injunctive relief.”
In Midwest Service Management, the Fifth District
Court of Appeals (which covers Licking and 13 other
Ohio Counties) applied the same reasoning from
Hardrives outside the context of construction. This
case dealt with a contract to purchase computers,
and the low bidder lost out because it had not bid on
either of the two brands of computer approved in the
specifications. Here, the unsuccessful bidder never
sought injunctive relief, asking instead for money
damages right away. In addition to questioning
whether the Midwest Service Management bid might
not indeed be non-responsive, the court found additionally
that “monetary damages are not available to
an unsuccessful bidder.”
Pointing to the reasoning in Hardrives, the court argued
what is basically a syllogism: Premise: If there
were a remedy at law (money damages), then injunctive
relief would not be available. Premise: We know
that injunctive relief is available because of cases like
Hardrives . Conclusion: Then a remedy at law must
not be available, and a disappointed bidder cannot
obtain money damages.
Mechanical Contractors. By the time the Midwest
Service Management, opinion came out, the court had to take into account one decision that went the other
way, at least in part: Mechanical Contractors Association
of Cincinnati, Inc. v. University of Cincinnati7. The Midwest Service Management court acknowledged
that Mechanical Contractors had
permitted an award of money damages, if proven, but
under different circumstances. In Mechanical Contractors,
the plaintiffs had first sought injunctive relief
unsuccessfully (something missing in the Licking
County case), and the plaintiff had been pursuing
their claims for years (again, unlike the bidder in Midwest
Service Management).
So why did the Mechanical Contractors case go a
different way from the other three? It was also a public
bidding case, but the initial question was whether
the competitive bidding statutes applied at all to the
construction of a University building by a private
developer who was leasing University land to build a
conference center that would then be leased back to
the University. The court decided that, despite the
lease/leaseback arrangement, the project should have
been competitively bid. But it was too late to turn
back the clock and start the construction all over again;
the building was too far along. The trial court granted
an injunction to restrain the University from ignoring
the public bidding laws, but the injunction applied
only to other, future projects.
The Court of Appeals for Franklin County looked at
other cases denying money damages to disappointed
bidders - including Hardrives and Cavanaugh - and
rejected their reasoning with this explanation:
At first blush, the above rationale upon which
monetary damages are denied is logical and
pragmatic. However, we are troubled by the
reality that the limited relief granted results
in a public entity’s potential ability to violate
laws intended to benefit the public without
fear of any meaningful reprisal which might
deter such violations in the future. In addition,
we are mindful of the fact that the
plaintiffs who pursue such litigation and prevail
in attaining a declaratory judgment
favorable to all taxpayers might have no recourse
in recouping financial losses incurred
in the process.
Without some form of money damages, the court felt
that the most the plaintiffs could recover for all their
efforts would be “a very expensive, hollow victory in
the form of a retrospective, virtually inconsequential
wrist-slap to the university and a prospective cautionary
declaration.” So the Court of Appeals sent
the case back to the trial court “for a determination of
the nature and extent of damages to be awarded.”
Eventually, the Mechanical Contractors case made
its way back to the Court of Appeals, where it was
decided that the plaintiffs had not proven their entitlement to any damages, which had been limited by
the trial court to their bid preparation costs. Focusing
on the issue of whether the bidders had a right to
rely on the University’s compliance with the competitive
bidding laws, the appellate court on the
second time around specifically did not address what
monetary damages would have been appropriate if
the plaintiffs had been able to prove they were entitled
to any.
So this was how the law stood before April 13, 2005:
Three different Courts of Appeals had held that
money damages in general and lost profits in particular
were not available to disappointed bidders,
for public policy reasons as well as the availability
of another remedy. Their only relief was to get
an injunction to stop the award of the contract to
another bidder, and if they had to appeal the denial
of that injunction, they should seek a stay of
the judgment so that the construction project
would not go forward during the appeal.
One court had disagreed, holding that, under certain
circumstances at least, money damages might
be available to a disappointed bidder who had
sought injunctive relief and been wrongly denied.
Those money damages might or might not include
lost profits, as the Court of Appeals never got to
that issue.
What Cementech Decided in April
On its second go-round at the appellate level, the
Cementech decision focused on two issues:
(1) Had the trial court erred in limiting monetary
damages to the costs of bid
preparation, rather than permitting an award
of lost profits? (2) Was it a mistake for the
trial court to prohibit an award of attorney’s
fees as a matter of law (decided by the
judge, not the jury)?
The second issue was an easy one for the
court. Cementech had failed to preserve
the issue of attorney’s fees for review, as it
had not presented a “proffer” of evidence
(a showing, outside the presence of the jury,
to indicate what evidence it would have presented
to the jury if it had been allowed to
do so). Without this proffer, the appellate
court refused to consider whether the trial
court had been right or not when it ruled
against the admission of such evidence.
But Issue Number 1 was not so easy. Cementech
argued that, as the jury had decided, its bid was lowest
and best, so it should have been awarded the
bid - or should at least have gotten its requested injunction
to prohibit the award to another bidder and
declare Cementech the rightful choice. But Cementech
was wrongly denied twice. Of course, the City saw it
another way, arguing - with the support of Hardrives,
Cavanaugh, and Midwest Service Management - that
the availability of injunctive relief meant that money
damages were not available, nor should they be, for
public policy reasons.
The court called the City’s argument based on the
availability of injunctive relief “illusory”:
Cementech requested injunctive relief and it
was denied. When it was determined that
Fairlawn abused its discretion and that
Cementech was the lowest and best bid and
thus, injunctive relief was improperly denied,
the project was already complete. With the
project complete, injunctive relief wrongfully
denied, a determination that Cementech was
the lowest and best bid, and a trial court ruling
limiting damages to bid preparation costs,
Cementech was left with inadequate relief.
In addition to allowing wrongfully rejected bidders “no
real relief,” the preclusion of monetary damages would
“allow government entities to go unpunished for ignoring
Ohio and municipal laws,” the court said. After
looking briefly at the public policy arguments in
Hardrives and the cases that followed it, the court
weighed one public policy against another,
concluding that “protecting the integrity
of the bidding process and ensuring
wronged parties receive meaningful relief
outweigh the risk of citizens paying twice
for the same project.”
So the court ruled that Cementech should
have been permitted to present evidence
of its lost profits and that the trial court
had erred in capping the monetary damages
at the cost of bid preparation.
It has been widely misreported that the
Court of Appeals ordered the City to repay
$90,922 in lost profits, but that is nowhere
in the opinion. Cementech did make a proffer
of what its evidence on lost profits
would have been, but according to David
Leneghan, attorney for Cementech, that
amount was $85,000. Robert Hunt, attorney
for the City, said that this proffer was
based on the profits envisioned by the second
lowest bidder, the contractor who
actually was awarded the job. Those anticipated
profits would seem to be a poor
yardstick to measure what profits might
have been earned had the contract been
awarded to a lower bidder.
In concluding its discussion of monetary damages,
the Court of Appeals ended with two paragraphs that
are sure to be quoted in many an argument about public
bidding for years to come:
This Court recognizes that we are setting a
precedent, but we find that our decision is necessary to protect the integrity of the bidding process and to ensure that government
entities take responsibility for their actions
and follow proper procedures and laws, thus
properly representing their constituents. We
find that Fairlawn must be held accountable
for abusing its discretion and that Cementech
must be able to present evidence of lost
profits.
We must note that the preferred method of
resolving bidding disputes is injunctive relief,
as that relief would prevent double
payment and better serve the integrity of the
bidding process. However, based on the facts
of this case, injunctive relief is no longer available
and the only available adequate remedy
for Cementech beyond costs for bid preparation
is lost profits. Compliance with bidding
procedures and thorough review of motions
for injunctive relief can reduce the necessity
of awarding lost profits.
What Happens Next?
The Court of Appeals clearly intended that the case
would go back to the trial court for a determination of
the amount of lost profits that Cementech should be
able to recoup from the City. But the appellate courts
may not be done yet. The City has already made a
motion to the Court of Appeals asking that court to
certify a conflict between its decision and Hardrives
and the two cases that follow its reasoning. The Court of Appeals granted that motion on May 5, 2005, narrowing the issue to this question: Does the availability of injunctive relief if timely filed but denied preclude an award of lost profits in a municipal contract case? The Supreme Court will accept briefs and hear arguments on that issue.
Even without a certified conflict, the City might have gotten its appeal heard by the Ohio Supreme Court if it could have made a sufficiently convincing case that the appellate court’s decision had created an issue “of public or great general interest” warranting further review.
What Should Happen While We Wait?
For the time being at least, one Court of Appeals has
set a precedent saying that a public owner who
wrongfully rejects a low bidder risks having to pay
whatever lost profits that low bidder can prove in
court. Nobody - neither owners nor contractors -
can afford to take that decision lightly. Until it is clear
whether the Supreme Court will tackle the issue and
what it may say if it does, everyone involved in public
bidding should take some extra precautions.
Public Owners. Public owners need to recognize
that they have more discretion to reject a bidder as
“not responsible” than they have to reject a bid as “not responsive.” The bid standards - lowest responsible
bidder (the standard for schools and libraries)
and lowest and best bidder (the standard for cities
and counties) - relate to the quality of the bidder. Bids
must also be responsive, that is, the bid must respond
to the bidding documents in all material respects and
contains no irregularities or deviations that would
affect the amount of the bid or give the bidder a competitive
advantage8.
Responsiveness deals with the
quality of the bid.
Anything public owners can do to incorporate responsiveness
into the announced criteria for
evaluating a bidder as responsible or the lowest and
best bidder should help their rejections to stand up in
court. For instance, it would help to announce that
one criterion for evaluating a bidder’s responsibility
will be the attention to detail demonstrated in its bid
preparation, with any deviation from the bid requirements
seen as one sign that the bidder might be equally
inattentive on the job.
The issue in Cementech involved an addendum.
Public owners should include specific provisions in
their Instructions to Bidders that address what happens
if a bidder does not acknowledge an addendum.
While these provisions cannot guarantee a result,
they should provide helpful guidance to a court that
is asked to review the public owner’s decision rejecting
a bid because the bidder failed to acknowledge an
addendum. The following is an example of such a
provision:
If a Bidder fails to indicate on its bid form
receipt of all Addenda through the last Addendum
issued by the Architect, the bid of
such Bidder will be deemed to be responsive
only if:
The bid received clearly indicates that the Bidder
received the Addendum, such as where the
Addendum added another item to be bid upon
and the Bidder submitted a bid on that item; or
The Addendum involves only a matter of form
or is one that either has no effect or has merely
a trivial or negligible effect on price, quantity,
quality, or delivery of the item bid upon.
Public owners also should consider including a provision
in their Instructions to Bidders that gives the
public owner the authority to make a final and binding
decision whether a bidder is the lowest
responsible bidder/lowest and best bidder and/or the
bidder’s bid is responsive. The following is an example
of such a provision:
By submitting its bid, the Bidder agrees that
the Owner’s determination of whether it is
the lowest responsible bidder (or lowest and
best bidder) and/or whether its bid is responsive shall be final and binding on the bidder
and all other persons.
If the public owner adopts this type of provision, it
should give the bidder a reasonable opportunity to
present its position for consideration.
Additionally, owners should take this opportunity to
review their bid evaluation and award procedures. In
most cases, the public owner, acting through its board
or council, must take official action in awarding
or rejecting a bid. If a bid is rejected, the
basis for the rejection should be specified
in the resolution. Depending on the facts
and the bid evaluation criteria, the basis for
the rejection could be because the bidder is
not a responsible bidder (or the lowest and
best bidder) and also because the bid was
not responsive. A bidder who makes a mistake
in its bid, a responsiveness issue, often
will have issues related to whether it is a
responsible bidder or the lowest and best
bidder as well.
Depending on the applicable bid award statute, the
public owner should consider rejecting all bids and
rebidding the project or applicable division of the Work.
Contractors. Contractors, in the midst of rejoicing
over the latest decision, may not realize that they need
to act, too. The Cementech case is not over yet, and it
is still not clear that Cementech will actually recoup
any of its anticipated lost profits. That depends not
just on what the Ohio Supreme Court may or may not
say; it also depends on Cementech’s ability to prove
what profits it would have made, had it gotten the contract.
The difficulty of such proof should be obvious. Profits
made by the same contractor on another job are not
necessarily proof of what it would have made on this
job. Nor are profits made or anticipated by a different
contractor on the same job. After all, that contractor
probably had different charges for overhead, different
allocations of its workforce, and a different - and
higher - bid to start with. Contractors need to anticipate,
as they prepare their bids, that they may someday
need to establish what profits they anticipated when
they were bidding the job. Whatever they can do at
this early stage to document the assumptions they made
about profits may prove beneficial if they turn out later
to be the low but disappointed bidder. Such documentation
could keep them from winning a “hollow victory”
saying they should have gotten the job but it is too
late to do more than reimburse them for the money
they lost in preparing their wrongly rejected bid.
We are sure the Cementech decision will continue to
be the topic of conversation for some time to come. Any new developments in the case will be covered in
future issues of this journal and ohioconstructionlaw.com.
Reprinted from Finley’s Ohio Municipal Service, with the permission of the
publisher and copyright owner, West Group.
|